Grants:IEG/Alt text tools/Finances

Budget

edit

Below is your approved budget. Please use this table to keep track of actual funds spent for each line item and list the difference from the approved budget at the end of the grant period.

Expense Approved amount Actual funds spent Difference
Software Development $6,000 USD $3,202.50 $2,797.50
Visual Design (UX and UI) $2,000.00 USD $1,050.00 $950.00
Documentation (well crafted and detailed) $2,000 USD $600.00 $1,400.00
Testing (to ensure accessibility of tool) $2,000 USD $1,200.00 $800.00
Travel (to support edit-a-thons and meetups) $500 USD $436.28 $63.72
Volunteer support (meeting spaces, refreshments, outreach) $1500 USD $272.45 $1,227.55
Total $14,000 USD $6,761.23 $7,238.77


Request changes

edit

We understand that sometimes plans change. Please use this button to request approval for changes to your grant’s budget while your project is in progress. Any variation of 20% or more to any line item in your budget must be approved by staff here before you make the change (for projects with budgets of $15,000 or more, the accepted variance is 10%).



More travel needed

edit

Budget change request

edit

I'd like the approval to move $750 of Volunteer Support to our travel line item. Thus making Volunteer Support total $750, and Travel be $1250

Rationale

edit

It's been much more expensive than we originally anticipated to travel to and from our meetings to facilitate the development and outreach of the grant.

I'm approving this request to transfer $750 from Volunteer Support to travel, as per this request. --Marti (WMF) (talk) 16:58, 14 March 2017 (UTC)